PMP考試每天一練--PMP考試試題-73
|
PMP考試試題一: Company ABC adopt year-summary for decritiation of asset. They spent $17,000 purchasing one computer. It is estimated that the computer can be sold with $2, 000 three years later. Thus, how much will be the asset decritiation of this computer in year three? A. 5000 B. 4500 C. 7500 D. 2500 ABC公司通常用年和法來計算資產的折舊。他們花1.7萬元買了一臺計算機,估計三年后能賣2000元。那么第三年的折舊是多少? A. 5000元 B. 4500元 C. 7500元 D. 2500元 PMP參考答案:D. 2500元 PMP答案解析:折舊--年數總和法 PMP考試試題二: Your manager gives you a project charter and asks you to begin working immediately and to provide her with a schedule. what should you do FIRST? A.Begin estimating the activities necessary to complete the scope of work. B.Begin creating a project scope statement C.Create an activity list and then begin to assign the activities to resources. D.Identify a team and obtain approval for their participation from their functional managers. 項目經理給了你項目章程后要求你立即開始工作,并要求提供給他進度計劃。此時,你首先應該做什么? A.估算活動以確定工作范圍。 B.開始制定項目范圍說明書。 C.開始制定活動清單,然后給活動分配資源。 D.確定團隊成員,并從職能經理那里獲得批準。 審題:此題關鍵字是“給了你項目章程后要求你立即開始工作,并要求提供給他進度計劃”“首先應該做什么”,很顯然在問在項目章程和進度計劃之間的項目步驟,可以從單個項目的項目管理過程章節之規劃過程組中查找,也可以從Rita流程圖中查找。 定位:規劃過程組·單個項目的項目管理 解析:在制定進度計劃之前,必須先完成范圍說明書和其他活動規劃。 規劃過程的第一步就是指定項目范圍說明書。故選項A、C和D開始之前必須先完成選項B所指的項目范圍說明書的制定。 PMP參考答案:B.開始制定項目范圍說明書。 |