PMP考試每天一練--PMP考試試題-47

轉載者:PMP團購網      發布時間:2017/1/10        點擊: 3260

PMP考試試題一:

Who controls the indirect (overhead) costs of a project?

A. Project manager

B. Executive management

C. Cost accounts manager

D. Internal auditor

是誰控制一個項目的間接成本(管理費)?

A. 項目經理

B. 高級管理層

C. 成本帳目經理

D. 內部審計員

PMP參考答案:B. 高級管理層

PMP答案解析:成本分類-間接成本

PMP考試試題二:

During the Define Activities process, a team member begins to discuss activities that the project manager has never heard discussed. What should the project manager do?

A. Make sure he has a good understanding of the activities and include the activities in the activity list.

B. Ask the team member to explain why such an activity would be needed to complete the work package.

C. Make sure the entire team agrees that the activities should be done.

D. Evaluate the impact of the change.

在定義活動過程中,一團隊成員開始討論一個項目經理從來沒有聽過的活動。此時項目經理應該怎么做?

A.確保團隊成員理解并將這些活動包含在活動清單里了。

B.詢問團隊成員需要完成這些活動的原因。

C.確認所有團隊成員都認同這些活動。

D.評估變更的影響。

審題: 此題的關鍵字為“定義活動”“討論”,項目進入規劃階段的范圍管理中的定義活動過程

定位: 規劃過程組·時間管理·6.2 定義活動

解析:

1、定義活動過程的目的是對活動(為完成工作包而必須開展的工作)進行定義,項目經理需要確認該活動是必須開展的;因此本題答案為B;

2、選項A活動清單是定義活動過程的輸出,排除;選項C是WBS的作用,排除;選項D為監控過程組的工作,排除;

3、此題的場景是干擾項,對選擇沒有作用,解題需要了解定義活動的目的和活動的定義。

答案:B.詢問團隊成員需要完成這些活動的原因。

閱讀本文的人還閱讀了:
PMP考試有題庫嗎?
PMBOK十大知識領域是什么?
PMP培訓機構是什么?
PMP認證流程是怎樣的?
怎么看PMP考試成績?
PMP考試報名費是多少?
PMP對企業有什么好處?

日韩精品一区二区三区三区免费_欧美理论片在线_久久精品人人做人人爽97 _欧美日韩亚洲视频

PMP團購導航
遠程PMP團購
北京PMP團購
上海PMP團購
廣州PMP團購
深圳PMP團購
江浙PMP團購
西部PMP團購
其他城市團購



PMP題庫
主站蜘蛛池模板: 丁香五月网久久综合| 日本一区免费| 日韩中文字幕在线免费观看| 国产精品自产拍高潮在线观看| 国产精品美女免费看| 国产精品久久久久福利| 国产视频不卡| 国产精品久久波多野结衣| 精品国产成人av在线免| 99在线影院| 国产精品久久久久久亚洲调教 | 国产午夜精品在线| 日韩日本欧美亚洲| www高清在线视频日韩欧美| 91精品国产91久久久久久久久| 国产高清在线一区| 国内一区二区在线视频观看| 亚洲a∨一区二区三区| 国产日韩在线免费v| 久久夜色精品国产亚洲aⅴ| 久久综合中文色婷婷| 久久99精品视频一区97| 久久777国产线看观看精品| 国产精品美女视频网站| 国产专区精品视频| 日韩网址在线观看| 久久6免费高清热精品| 国产精品一区二区性色av| 国产精品一区二区性色av| 日本精品久久久久久久久久| 欧美在线观看日本一区| 国产精品视频免费观看www| 欧美,日韩,国产在线| 亚洲欧美日韩精品久久久| 中文字幕久久综合| 亚洲一区高清| 亚洲精品蜜桃久久久久久| 久久久久久草| 久久视频国产精品免费视频在线| 欧美精品久久久| 亚洲五月六月|