PMP考試每天一練--PMP考試試題-46
|
PMP考試試題一: The summary milestone schedule and summary budget have just been determined. What project management process group are you in? A. Initiating B. Planning C. Executing D. Monitoring and controlling 已經(jīng)確定了總體里程碑計劃和總體預算,那么項目處于哪個管理過程組? A. 啟動 B. 規(guī)劃 C. 執(zhí)行 D. 監(jiān)控 PMP參考答案:A. 啟動 PMP答案解析:項目章程(4.1.3.1)P71 PMP考試試題二: A project manager meets with a resource manager and asks to move resources from project A to project B. What is the MOST likely reason for this request? A. A problem has caused delay beyond the project manager’s ability to control. B. Project A has become higher priority within the organization. C. An activity has taken longer than planned. D. An activity was missed because a work breakdown structure was not created. 項目經(jīng)理會見資源經(jīng)理,希望把項目A的資源借調給項目B。發(fā)生此問題的最可能的原因是什么? A. 發(fā)生了問題導致項目進度延后,進度落后的程度超出了項目經(jīng)理控制能力。 B. 項目A在公司開始擁有更高的優(yōu)先級。 C. 完成活動的時間比預期的要長。 D. 沒有制定工作分解結構,導致某項活動遺漏。 審題: 此題的關鍵字為“資源經(jīng)理”和“資源借調”,意思就是什么原因下超出了項目經(jīng)理能自己處理的范圍需要求助于資源經(jīng)理,考查的是項目執(zhí)行過程中哪些情況是超出項目經(jīng)理能處理的能力之外的。 定位: 執(zhí)行過程組·整合管理·4.3 指導與管理項目工作 解析: 1、 如果項目A擁有了更高的優(yōu)先級,那么資源就會直接分給項目A,而非借調了,選項B不正確。 2、 如果C和D的情況發(fā)生,應該在項目的約束條件內解決,而不是直接去移動資源。 答案:A. 發(fā)生了問題導致項目進度延后,進度落后的程度超出了項目經(jīng)理控制能力。 |