PMP考試每天一練--PMP考試試題-34
|
PMP考試試題一: A project manager discovers that a work package has been completed for substantially less cost than planned. Which of the following is NOT among the first things to consider doing? A. Make sure all project processes were followed. B. Make sure the right resources were used. C. Make sure all the work was done. D. Identify ways to increase the result. 項目經(jīng)理發(fā)現(xiàn),某一工作包實際花費比預算少很多。以下都是首先要考慮做的事情,除了: A. 確保遵循了所有的項目流程。 B. 確保合理地使用了資源。 C. 確保所有工作已經(jīng)完成。 D. 識別增加結(jié)果的各種方法。 PMP參考答案:D. 識別增加結(jié)果的各種方法。 PMP答案解析:控制成本工具-績效審查(7.4.2.4)P223 PMP考試試題二: A team member comes to you to tell you that there is a problem on her activity. It cannot be started on the day it is scheduled to start. A manager overhears this conversation and reports that the project will be late. Later the project manager completes his own report saying “the project is still scheduled to be completed on time.” Which of the following could be the reason the project manager made such a statement? A. The activity has free float and can be rescheduled later in its early-start to late-finish window. B. The activity is on a near-critical path with less float than the length of the delay. C. The activity is on the critical path but is to be done after another activity that does have D. The activity has a mandatory dependency, allowing the project manager to place it in the project schedule at any location that he wants it to be done. 一團隊成員過來告訴你,她負責的活動出了問題,不能在預期規(guī)定的開始時間啟動。一位經(jīng)理偷聽到了你們的談話并報告管理層說項目將要延期。項目經(jīng)理在后續(xù)的進度報告總說:“項目在進度計劃內(nèi),而且會按時完成。”以下哪項可能是項目經(jīng)理如此匯報的原因? A. 此活動有浮動時間,可以重新安排它的最早開始時間和最晚結(jié)束時間。 B. 活動在近關(guān)鍵路徑上,活動的浮動時間比延期的時間要短。 C. 活動在關(guān)鍵路徑上,但在另外有浮動時間活動結(jié)束之后才能開始。 D. 活動有強制依賴關(guān)系,所以項目經(jīng)理可以把它隨意安排在進度中的任何位置。 審題: 此題的關(guān)鍵字為“……項目在進度計劃內(nèi),而且會按時完成……”,題干提到的某一活動出了問題,不能在預期規(guī)定的時間啟動,但沒有提到此活動在關(guān)鍵路徑上,理解這一點即為解題關(guān)鍵。 定位: 解析: 1、題干提到的某一活動出了問題,不能在預期規(guī)定的時間啟動,但項目經(jīng)理在報告中指出項目在進度計劃內(nèi),由此可以分析出此活動不在關(guān)鍵路徑上,而且此延期的活動有浮動時間,不影響總工期。所以A是正確答案; 2、B答案“活動的浮動時間比延期的時間要短”,如果此活動的浮動時間短,那么它必將導致項目延期,答案B錯誤;活動不在關(guān)鍵路徑上,C答案也是錯誤的;有強制依賴關(guān)系的活動不能隨意安排其在進度中的位置所以D答案錯誤。 PMP參考答案:A. 此活動有浮動時間,可以重新安排它的最早開始時間和最晚結(jié)束時間。 |