PMP考試每天一練--2016年PMP考試模考試題-9
|
PMP英文試題:9. A company’s management team wants to hire a resource to manage a software update to the company’s existing product; the product is one of several in a department that has other important activities. Which of the following candidates should be selected to manage the software update? A. Experienced software developer B. External consultant C. Department manager D. Part-time project manager PMP中文翻譯:9.一家公司的管理團隊希望雇傭一名資源,來管理對公司現有產品的軟件升級。該產品是某個部門多個產品的其中一個產品,且該部門還有其它重要活動.那么應該選擇下列哪一個候選人來管理軟件更新? A. 經驗豐富的軟件開發人員 B. 外部顧問 C. 部門經理 D. 兼職項目經理 PMP參考答案:D 兼職項目經理 PMP答案解析:項目的特點 ( 1.2) |