PMP考試每天一練--2016年P(guān)MP考試模考試題-5
|
PMP試題5. You are assigned project manager in executing project; the project is in control on baseline, if customers are not satisfied with the performance, then what you should do firstly? A. Discussing with project team B. Baseline revised C. Contract Renegotiation D. Meeting with customers PMP試題5.在項(xiàng)目執(zhí)行過(guò)程中,你被任命為項(xiàng)目經(jīng)理。項(xiàng)目各項(xiàng)指標(biāo)都在基線的允許范圍內(nèi),如果客戶對(duì)項(xiàng)目績(jī)效不滿意,你首先應(yīng)該做什么? A. 與項(xiàng)目團(tuán)隊(duì)一起討論 B. 重新計(jì)算基線 C. 重新商談合同 D. 與客戶見(jiàn)面 參考答案:D 考題解析:控制干系人參與工具-會(huì)議(13.4.2.3)P413 |