PMP考試題----項(xiàng)目人力資源管理題目11-15:11. In order for project managers to be effective, they must:
A. Continue to be actively involved in their technical field of expertise
B. Actively participate with other management personnel in planning the project
C. Monitor and control all task of the project to the lowest level of the WBS
D. Control the functional manager’s personnel on all project aspects
為了使項(xiàng)目經(jīng)理的工作更有效,他們必須:
A. 繼續(xù)熱情的專注于專業(yè)技術(shù)領(lǐng)域
B. 主動與其他的管理人員一起編制項(xiàng)目計(jì)劃
C. 檢查控制WBS 最底層的所有工作
D. 控制項(xiàng)目的各個(gè)方面職能型經(jīng)理下屬的人員
12. What is the process that the project manager uses to coordinate the efforts of workers toward the accomplishment of group(project) goals?
A. Integration of skills
B. Procurement management
C. Leadership
D. Problem solving
為了努力完成項(xiàng)目目標(biāo),項(xiàng)目經(jīng)理經(jīng)常用來協(xié)調(diào)項(xiàng)目人員投入的過程是什么?
A. 整合技能
B. 采購管理
C. 領(lǐng)導(dǎo)能力
D. 解決問題的能力
13. Which of the following is NOT critical action for the project manager to take in the integration process for a matrix organization?
A. Planning for integration
B. Development of an integrated WBS, schedule, and budget
C. Provide technical training for the project team members
D. Resolve customer problems
項(xiàng)目經(jīng)理在對矩陣型組織實(shí)施一個(gè)整合過程時(shí),下面的哪個(gè)做法不是關(guān)鍵的:
A. 整合計(jì)劃
B. 制定集成的WBS,日程安排和預(yù)算
C. 為項(xiàng)目成員提供技術(shù)培訓(xùn)
D. 解決客戶的問題
14. Which of the following is NOT a form of power that the project manager can use due to the position of project manager in the company?
A. Formal
B. Reward
C. Penalty
D. Expert
在公司里,下面哪個(gè)不屬于項(xiàng)目經(jīng)理在其職位上可以行使的權(quán)力?
A. 正式的權(quán)力
B. 獎(jiǎng)勵(lì)權(quán)
C. 處罰權(quán)
D. 專家權(quán)
15. Which of the following is NOT an organizational form?
A. Functional organization
B. Matrix organization
C. Projectized organization
D. Project expediter
下面的哪個(gè)不屬于組織的形式:
A. 職能型組織
B. 矩陣型組織
C. 項(xiàng)目型組織
D. 項(xiàng)目聯(lián)絡(luò)人
PMP考試題的參考答案: 11-15 BACDD